Vaira (353) 2003-12-19 14:00:00 Ted Hehn Clean and install batteries, upload data.
Vaira (352) 2003-12-18 00:00:00 Ted Hehn Replace hard drive from laptop, move precip gauge, moisture profile data.
Tonzi/Vaira (331) 2003-11-27 09:00:00 Ted Hehn CR10X2 needs new battery, fixed grounding on CR10X2, CR23X3 and muxes
Tonzi/Vaira (314) 2003-11-10 09:00:00 LiuKang Xu Duplicate of 11-7 notes which covers both days
Vaira (312) 2003-11-08 00:00:00 Ted Hehn Flux platform not operational, fix and check other systems.
Tonzi/Vaira (311) 2003-11-07 09:00:00 LiuKang Xu First heavy rain of the season, Vaira solar controller burned - replaced, Oak DBH expand quickly after rain.
Tonzi (291) 2003-10-18 00:00:00 Ted Hehn Regular data download.
Vaira (291) 2003-10-18 00:00:00 Ted Hehn Regular data download.
Tonzi/Vaira (275) 2003-10-02 05:30:00 LiuKang Xu Last predawn water potential of season, swapped 7500s, Vaira on day light savings time for about a week.
Tonzi (261) 2003-09-18 18:00:00 Ted Hehn Repair CO2 profile and soil temp profile.
Vaira (261) 2003-09-18 09:00:00 Ted Hehn Replace PC, lost communication between data loggers.
Tonzi (254) 2003-09-11 00:00:00 Ted Hehn Data download, routine site visit.
Vaira (254) 2003-09-11 00:00:00 Ted Hehn Data collection.
Tonzi/Vaira (248) 2003-09-05 04:30:00 LiuKang Xu Predawn water potential, Soil temperature and heat flux readings bad, lost some flux at Vaira
Tonzi/Vaira (242) 2003-08-30 10:00:00 Ted Hehn Standard fieldwork, wind profile heights
Tonzi (212) 2003-07-31 09:00:00 Dennis Baldocchi Show and tell, standard systems check
Tonzi/Vaira (206) 2003-07-25 10:00:00 Ted Hehn Fix CO2 profile system at Tower, all okay
Tonzi/Vaira (206) 2003-07-25 10:00:00 LiuKang Xu New laptop for Floor site, Tower wind profile system running, GPS locations, ACi curves
Tonzi/Vaira (198) 2003-07-17 10:00:00 LiuKang Xu Standard fieldwork, installed two more soil co2 sensors at -24cm, leaf samples for CASI image - 9 plots
Tonzi/Vaira (192) 2003-07-11 04:30:00 LiuKang Xu Predawn water potential, standard fieldwork, path around Floor site
Vaira (187) 2003-07-06 00:00:00 Ted Hehn Check data loggers.
Tonzi/Vaira (184) 2003-07-03 10:00:00 Dennis Baldocchi Standard fieldwork, changed heading of Floor net radiometer to avoid foot path, brought booms for Handar wind profile
Tonzi/Vaira (178) 2003-06-27 10:00:00 Ted Hehn Beginning to install booms for Handar wind profile, Vaira all seems well
Tonzi (177) 2003-06-26 10:00:00 Ted Hehn Troubleshooting CR10x5 and CR10x6
Tonzi/Vaira (171) 2003-06-20 04:35:00 LiuKang Xu Predawn water potential, swapped all 7500s, One Vaisala co2 probe died.
Tonzi/Vaira (164) 2003-06-13 11:25:00 LiuKang Xu Calibrated LI-800 Tower co2 profile, bird poop on tower 7500, six clip plots at Vaira
Tonzi (164) 2003-06-13 11:00:00 Ted Hehn Calibrated li-800 Tower co2 profile. Tried new program for the profile but no good - back to old program
Tonzi/Vaira (160) 2003-06-09 08:00:00 Theresa Krebs Marathon 6400 measurements day 4.
Tonzi/Vaira (158) 2003-06-07 04:30:00 Theresa Krebs Marathon 6400 measurements day 2
Tonzi/Vaira (157) 2003-06-06 12:00:00 Dennis Baldocchi Standard data download and systems check
Tonzi/Vaira (150) 2003-05-30 13:30:00 Ted Hehn Emergency trip to fix Floor system - dead sonic and IRGA taken to Vaira
Tonzi/Vaira (150) 2003-05-30 04:24:00 LiuKang Xu Predawn water potential, Floor sonic dead, Vaira 7500 power connector bad, moved Floor 7500 to Viara
Tonzi/Vaira (141) 2003-05-21 09:10:00 LiuKang Xu Lost 11 days of IRGA data at Vaira due to bad connection, standard fieldwork
Tonzi (134) 2003-05-14 00:00:00 Ted Hehn Install CO2 profile system, zero/span equipment.
Tonzi/Vaira (129) 2003-05-09 04:45:00 LiuKang Xu Predawn water potential, swapped 7500s, move tree soil co2 profile due to gophers, li-6400 measurements
Tonzi/Vaira (120) 2003-04-30 00:00:00 Dennis Baldocchi Standard fieldwork, added equipment to connect new Tower CO2 profile system to MD9 network but not finished yet.
Tonzi/Vaira (106) 2003-04-16 08:15:00 LiuKang Xu Heavy previous two days, light rain today. Grass is peak, all looks well, Two ACi curves
Vaira (98) 2003-04-08 09:20:00 Ted Hehn Finish tower power upgrade and install CO2 profile system.
Vaira (96) 2003-04-06 17:00:00 Ted Hehn Replace Li7500s
Vaira (95) 2003-04-05 00:00:00 Ted Hehn Finish tower power upgrade and install CO2 profile system.
Vaira (94) 2003-04-04 00:00:00 Ted Hehn Finish tower power upgrade and install CO2 profile system.
Vaira (93) 2003-04-03 00:00:00 Ted Hehn Finish tower power upgrade and install CO2 profile system.
Vaira (89) 2003-03-30 10:00:00 Ted Hehn Download data, all okay
Tonzi (89) 2003-03-30 09:00:00 Ted Hehn Finish Tower power upgrade, problems with PC restarts not getting sonic serial data.
Tonzi (88) 2003-03-29 09:00:00 Ted Hehn Continue working on solar power upgrade.
Tonzi (87) 2003-03-28 09:00:00 Ted Hehn Checking on systems both Tower and Floor locked up. Starting Tower solar power upgrade
Tonzi (80) 2003-03-21 00:00:00 Ted Hehn Download data, install new tower power enclosure, repair data logger.
Vaira (79) 2003-03-20 00:00:00 Ted Hehn Repair and replace data logger, install new tower power regulator enclosure, download data.
Tonzi/Vaira (76) 2003-03-17 10:45:00 LiuKang Xu Heavy rain yesterday, swapped Tower and Floor 7500s, water in tower top 23x box, Tonzi computer clocks 14min fast - reset, Jianwu did soil respiration
Vaira (62) 2003-03-03 00:00:00 Ted Hehn Replace fence battery at Vaira
Tonzi (62) 2003-03-03 00:00:00 Ted Hehn Data collection.
Tonzi/Vaira (58) 2003-02-27 10:00:00 Dennis Baldocchi Tonzi set laptop times, compared HMP45s Tower RH low, Swapped Tower top CR23x, Fixed wiring on HFP 3 at Vaira
Tonzi/Vaira (52) 2003-02-21 10:00:00 LiuKang Xu Vaira down from blown fuse - disconnected two solar panels, Tower top CR23x not communicating
Tonzi (44) 2003-02-13 10:00:00 Ted Hehn New batteries at Tower, down load data, checked HFP #4, new keyboard for Floor PC
Vaira (44) 2003-02-13 00:00:00 Ted Hehn Added batteries, check soil moisture, download data.
Tonzi/Vaira (34) 2003-02-03 10:00:00 Ted Hehn Vaira new battery box, added fuses to solar system, new fence battery
Tonzi/Vaira (29) 2003-01-29 11:00:00 LiuKang Xu Swapped 7500s at all towers, Tower down due to burn out of solar controller,
Tonzi (29) 2003-01-29 10:00:00 Ted Hehn Tower solar controller melted terminal - fix but swapped for soil co2 system. New ventilated HMP45 shield, change solar panel angle, leveled net radiometers.
Tonzi/Vaira (21) 2003-01-21 09:00:00 Ted Hehn New CR10x program for diffuse PAR and 4-way net radiaometers, swapped HMP45 at Tonzi
Tonzi (13) 2003-01-13 00:00:00 Ted Hehn Zero/span Li800.
Vaira (8) 2003-01-08 00:00:00 Ted Hehn Order materials for Jianwu's site.
Vaira (7) 2003-01-07 14:00:00 Ted Hehn Battery box destroyed, replaced keyboard on laptop, Found wiring problem in solar panels - half no connected, Add diffuse and 4-way radiometer?
 
 