SiteDateAuthorSummary
Tonzi (353) 2018-12-19 10:00:00 Joe Verfaillie Change FLIR restart time, Surface temp on OSU SP2 and SP3, LWin and LWout on SP1.
Tonzi (353) 2018-12-19 09:00:00 Siyan Ma Dennis found old well at Vaira, cleaned up wire from litter cages at Tonzi, standard field work
Tonzi (347) 2018-12-13 11:30:00 Joe Verfaillie Power upgrade at the Floor site and soil co2 system, FLIR cal plane misaligned.
Tonzi (337) 2018-12-03 11:30:00 Joe Verfaillie Things are wet and green from first rains last week, fixed cow fences, two dead trees fell, FLIR cal panel twisted.
Tonzi (318) 2018-11-14 10:00:00 Joe Verfaillie Standard fieldwork, affixed FW TC to FLIR window, added TCs to FLIR cal panel
Tonzi (318) 2018-11-14 00:00:00 Siyan Ma Standard data collection, grass and oak litter collected
Tonzi (311) 2018-11-07 11:30:00 Joe Verfaillie Check Floor batteries, soilco2 power, temp fences around Floor, retested OSU SP2 and SP3 rain buckets, checked on FLIR system, cleaned Phenocam window.
Tonzi (302) 2018-10-29 10:00:00 Siyan Ma JPL installing equipment, testing tipping buckets, power problems at Floor and soil co2, checked SMAP nodes
Tonzi (302) 2018-10-29 10:00:00 Joe Verfaillie JPL installing equipment, testing tipping buckets, power problems at Floor and soil co2, checked SMAP nodes
Tonzi (290) 2018-10-17 11:30:00 Joe Verfaillie Maintenance trip, tested tipping buckets, fixed FLIR focus, split loom on radiometer wires, checked IRT battery.
Tonzi (285) 2018-10-12 10:30:00 Joe Verfaillie Standard fieldwork - all seems well
Tonzi (270) 2018-09-27 10:10:00 Joe Verfaillie Standard fieldwork, Added SSR to FLIR to to cycle once a day, tried LattePanda again, reset dendrometers, swapped 7500s
Tonzi (256) 2018-09-13 00:00:00 Joe Verfaillie Changed Tower Top CR1000 program, added thremocouples to FLIR case, FLIR locked up this time, reset some of the dendrometers, JPL setting up their solar panels.
Tonzi (242) 2018-08-30 10:00:00 Joe Verfaillie Standard fieldwork. problems with the Latte Panda and the FLIR, and the pressure bomb.
Tonzi (222) 2018-08-10 11:00:00 Joe Verfaillie Hot and dry, changed Tower co2 profile program, new CF card for phenocam, swapped battery at road well.
Tonzi (222) 2018-08-10 09:00:00 Siyan Ma Standard fieldwork, midday water potential, went to the pond, hot, tree greenness declining.
Tonzi (199) 2018-07-18 09:10:00 Joe Verfaillie Met JPL to plan radiometer install, Moved FLIR camera and black panel.
Tonzi (177) 2018-06-26 11:30:00 Joe Verfaillie Inventoried OSU equipment, swapped 7500s, watered soil CO2 batteries, standard fieldwork.
Tonzi (156) 2018-06-05 11:15:00 Joe Verfaillie Standard fieldwork, added water to batteries, replaced Tower HMP45 fan, explored other locations for the FLIR camera
Tonzi (156) 2018-06-05 10:00:00 Siyan Ma Replaced VR soil co2 batteries, thermal camera work at TZ, standard fieldwork, grass samples, midday water potential.
Tonzi (152) 2018-06-01 10:30:00 Joe Verfaillie Installed FLIR A325sc thermal camera, check phenocams
Tonzi (143) 2018-05-23 11:00:00 Joe Verfaillie Standard data collection, lots of flowers, removed LED sensor and old LI-820 CO2 profile from the Tower.
Tonzi (143) 2018-05-23 10:00:00 Siyan Ma Standard field work, grass about 50% brown/yellow
Tonzi (131) 2018-05-11 11:00:00 Joe Verfaillie Installed Global Water logger at Road Well, problems with new CF card for phenocam image collection, standard fieldwork, midday water potential
Tonzi (115) 2018-04-25 10:30:00 Joe Verfaillie Missing Phenocam image, replaced clock batteries in zcam 2 and 3, checking solar equipment
Tonzi (115) 2018-04-25 09:00:00 Siyan Ma Very green, grasses maybe just passed peak, Ana did ASD spectra, standard fieldwork, midday water potential
Tonzi (103) 2018-04-13 10:00:00 Joe Verfaillie Standard field work, spectra library with ASD, first leaf water potential, removed northeast sap flow station.
Tonzi (103) 2018-04-13 09:00:00 Siyan Ma Standard field work, very green, first water potential measurements of the year, Ana did spectra at Tonzi
Tonzi (86) 2018-03-27 10:30:00 Joe Verfaillie Trees starting to put on leaves, fixed CR200, removed old well logger, turned off old Tower co2 profile, LAI-2200 measurements, replaced IRT tripod.
Tonzi (65) 2018-03-06 10:30:00 Joe Verfaillie Downgraded LI-7550 boxes, swapped 7500 heads, still trying to get of Tower co2 profile to run, still trying to get tower computer to run, still trying to get well and zcam 3 to run.
Tonzi (65) 2018-03-06 09:00:00 Siyan Ma Standard fieldwork, clip plots, swapped 7500 heads
Tonzi (59) 2018-02-28 11:00:00 Joe Verfaillie Installed Tower computer but no modem, upgraded power connections, updated GMP343 profile program, updated Floor well/zcam program
Tonzi (52) 2018-02-21 10:00:00 Joe Verfaillie Tried to set up Tower computer again, restarted old li-820 co2 profile, copied z-cam CR10X program.
Tonzi (52) 2018-02-21 09:00:00 Siyan Ma Standard fieldwork, lost Vaira Phenocam images,new well sensor
Tonzi (38) 2018-02-07 11:00:00 Joe Verfaillie Finished new Vaisala co2 profile, tried to install Latte Panda, Installed new well sensor, IRT tripod down - fixed.
Tonzi (38) 2018-02-07 09:00:00 Siyan Ma Unusually warm and sunny, missing images, new Tower co2 profile, new well sensor, clip plots, IRT tripod down - fixed.
Tonzi (15) 2018-01-15 11:30:00 Joe Verfaillie Partially installed new GMP343 co2 profile on the tower, removed the FD chamber for Tree 1 soil co2 profile.
Tonzi (15) 2018-01-15 10:00:00 Siyan Ma Foggy, standard fieldwork, removed Forced Diffusion chambers
Tonzi (3) 2018-01-03 10:45:00 Joe Verfaillie Fixed z-cam clocks, few Phenocam images
Tonzi (3) 2018-01-03 10:00:00 Siyan Ma Standard fieldwork, collected clip plots, calibrated soil co2 Vaisala