Tonzi (352) 2011-12-18 00:00:00 Siyan Ma checked and downloaded data at Tower, Floor, and Vaira, Swapped Li-7500 at TZ Tower and Floor, Li-800 showed "-9999", not working in the field, taken back to the lab, Collected oak litter of this fall within 1x1 m2 square
Tonzi (335) 2011-12-01 10:00:00 Joe Verfaillie Check Stardot, replace SFH5, brought sap flow serial lines out of the trees, fixed sap flow west and south.
Tonzi (335) 2011-12-01 09:00:00 Siyan Ma Standard field work. Laurie and Erika tried soil cores and tree cores.
Tonzi (320) 2011-11-16 12:00:00 Joe Verfaillie Fixed Stardot ethernet, removed N2 scrub and recaled LI810, Changed cr10x2_soiltemp program, fixed two STC and removed SHF5, serviced z-cams.
Tonzi (313) 2011-11-09 09:20:00 Siyan Ma Standard field work.
Tonzi (306) 2011-11-02 10:00:00 Joe Verfaillie Checked refocused Stardot camera, fixed labels in Loggernet on floor computer, replaced flowmeter in co2 profile system, did EMI survey, cleaned z-cam windows, tree circumfrence.
Tonzi (299) 2011-10-26 09:30:00 Joe Verfaillie Swapped CO2 profile IRGA, possibly sticky solinoid, sticky flow meter, fixed focus and network for stardot camera, serviced z-cams.
Tonzi (299) 2011-10-26 09:00:00 Siyan Ma Standard field work, Fixed CO2 profile system.
Tonzi (291) 2011-10-18 09:30:00 Joe Verfaillie Swapped Floor 7500, Installed Stardot camera. Did EMI survey.
Tonzi (286) 2011-10-13 11:00:00 Joe Verfaillie Swapped LI800-820, Walked EMI survey.
Tonzi (286) 2011-10-13 11:00:00 Siyan Ma Grass is up, Vaira 7500 down and swapped with Frank's, Stardot camera added to Vaira, swapped co2 profile IRGA, EMI survey.
Tonzi (272) 2011-09-29 10:00:00 Siyan Ma Standard fieldwork, CO2 profile system not working, error message on Floor computer.
Tonzi (266) 2011-09-23 10:00:00 Joe Verfaillie EMI survey, Tower IRGA blocked by bird dropping - cleaned, Floor computer okay, Dead tree list, changed z-cam programs.
Tonzi (259) 2011-09-16 09:00:00 Joe Verfaillie Rebuilt Floor solar battery pack. Replaced Floor computer.
Tonzi (243) 2011-08-31 09:30:00 Joe Verfaillie Standard field work, new sunset z-cam program works, strange growths on tree leaves, broke tree corer, trees beginning to yellow.
Tonzi (221) 2011-08-09 09:30:00 Joe Verfaillie Standard field work. Fixed adjusted zcam programs for sunset refference, Floor computer hung in boot, MD9 connections unstable, tree 4cm co2 probe bad.
Tonzi (201) 2011-07-20 12:30:00 Joe Verfaillie Change z-cam 1 and 2 program to sunset version, measured tower instruments.
Tonzi (187) 2011-07-06 11:00:00 Siyan Ma Need new tank for water potetial, PC at Vaira crashed - restarted, maybe need fan for box, swapped LI7500 at TZ Tower and Vaira.
Tonzi (166) 2011-06-15 11:00:00 Siyan Ma Standard fieldwork, midday water potential.
Tonzi (154) 2011-06-03 10:30:00 Joe Verfaillie Setting up isoprene REA system, z-cam service, fix renaming time on floor computer, reset tower sonic/IRGA mount.
Tonzi (147) 2011-05-27 09:30:00 Siyan Ma Standard field work and met with University of Michigan group intersted in soil moisture.
Tonzi (130) 2011-05-10 08:20:00 Joe Verfaillie COSMOS probe install, Finishing root survey, Standard field work.
Tonzi (125) 2011-05-05 09:30:00 Joe Verfaillie Continuing root survey with GPR, pits and cores.
Tonzi (124) 2011-05-04 09:00:00 Joe Verfaillie Continuing root survey with GPR, pits and cores.
Tonzi (123) 2011-05-03 09:30:00 Joe Verfaillie Beginning or root survey with GPR, pits, and cores.
Tonzi (112) 2011-04-22 00:00:00 Siyan Ma Tower Li-7500 worked well
Tonzi (105) 2011-04-15 12:00:00 Joe Verfaillie Serviced z-cams - advanced image collection one hour, Fixed unsetup DAC channels on tower LI-7500, changed co2 profile filters.
Tonzi (105) 2011-04-15 00:00:00 Siyan Ma Tonzi: 100% oak leaf out
Tonzi (89) 2011-03-30 10:45:00 Joe Verfaillie swapped tower LI7500, serviced z-cams, fixed water pluggin lowest co2 profile inlet, new fan from floor HMP45.
Tonzi (89) 2011-03-30 00:00:00 Siyan Ma tree leaf start coming out
Tonzi (70) 2011-03-11 10:30:00 Joe Verfaillie Swapped solar power battery bank, restarted co2 profile.
Tonzi (67) 2011-03-08 11:00:00 Joe Verfaillie Fixed tram, Moved tipping bucket, updated soil co2 data logger program, fixed all cow fences, serviced z-cams, fixed west sap flow station.
Tonzi (53) 2011-02-22 00:00:00 Siyan Ma Tower batteries need to be replaced because no nighttime data.
Tonzi (34) 2011-02-03 12:15:00 Joe Verfaillie Swapped tram battery, collected data, spectra, moisture point. Brought in floor supplimental sensors.
Tonzi (19) 2011-01-19 00:00:00 Siyan Ma power problem at Vaira and Tonzi-Tower
Tonzi (5) 2011-01-05 08:00:00 Siyan Ma Installed new computer at Floor site, swapped Floor and Tower LI-7500.