Site | Date | Author | Summary |
Tonzi |
(353) 2018-12-19 10:00:00 |
Joe Verfaillie |
Change FLIR restart time, Surface temp on OSU SP2 and SP3, LWin and LWout on SP1.
|
Tonzi |
(353) 2018-12-19 09:00:00 |
Siyan Ma |
Dennis found old well at Vaira, cleaned up wire from litter cages at Tonzi, standard field work
|
Tonzi |
(347) 2018-12-13 11:30:00 |
Joe Verfaillie |
Power upgrade at the Floor site and soil co2 system, FLIR cal plane misaligned.
|
Tonzi |
(337) 2018-12-03 11:30:00 |
Joe Verfaillie |
Things are wet and green from first rains last week, fixed cow fences, two dead trees fell, FLIR cal panel twisted.
|
Tonzi |
(318) 2018-11-14 10:00:00 |
Joe Verfaillie |
Standard fieldwork, affixed FW TC to FLIR window, added TCs to FLIR cal panel
|
Tonzi |
(318) 2018-11-14 00:00:00 |
Siyan Ma |
Standard data collection, grass and oak litter collected
|
Tonzi |
(311) 2018-11-07 11:30:00 |
Joe Verfaillie |
Check Floor batteries, soilco2 power, temp fences around Floor, retested OSU SP2 and SP3 rain buckets, checked on FLIR system, cleaned Phenocam window.
|
Tonzi |
(302) 2018-10-29 10:00:00 |
Siyan Ma |
JPL installing equipment, testing tipping buckets, power problems at Floor and soil co2, checked SMAP nodes
|
Tonzi |
(302) 2018-10-29 10:00:00 |
Joe Verfaillie |
JPL installing equipment, testing tipping buckets, power problems at Floor and soil co2, checked SMAP nodes
|
Tonzi |
(290) 2018-10-17 11:30:00 |
Joe Verfaillie |
Maintenance trip, tested tipping buckets, fixed FLIR focus, split loom on radiometer wires, checked IRT battery.
|
Tonzi |
(285) 2018-10-12 10:30:00 |
Joe Verfaillie |
Standard fieldwork - all seems well
|
Tonzi |
(270) 2018-09-27 10:10:00 |
Joe Verfaillie |
Standard fieldwork, Added SSR to FLIR to to cycle once a day, tried LattePanda again, reset dendrometers, swapped 7500s
|
Tonzi |
(256) 2018-09-13 00:00:00 |
Joe Verfaillie |
Changed Tower Top CR1000 program, added thremocouples to FLIR case, FLIR locked up this time, reset some of the dendrometers, JPL setting up their solar panels.
|
Tonzi |
(242) 2018-08-30 10:00:00 |
Joe Verfaillie |
Standard fieldwork. problems with the Latte Panda and the FLIR, and the pressure bomb.
|
Tonzi |
(222) 2018-08-10 11:00:00 |
Joe Verfaillie |
Hot and dry, changed Tower co2 profile program, new CF card for phenocam, swapped battery at road well.
|
Tonzi |
(222) 2018-08-10 09:00:00 |
Siyan Ma |
Standard fieldwork, midday water potential, went to the pond, hot, tree greenness declining.
|
Tonzi |
(199) 2018-07-18 09:10:00 |
Joe Verfaillie |
Met JPL to plan radiometer install, Moved FLIR camera and black panel.
|
Tonzi |
(177) 2018-06-26 11:30:00 |
Joe Verfaillie |
Inventoried OSU equipment, swapped 7500s, watered soil CO2 batteries, standard fieldwork.
|
Tonzi |
(156) 2018-06-05 11:15:00 |
Joe Verfaillie |
Standard fieldwork, added water to batteries, replaced Tower HMP45 fan, explored other locations for the FLIR camera
|
Tonzi |
(156) 2018-06-05 10:00:00 |
Siyan Ma |
Replaced VR soil co2 batteries, thermal camera work at TZ, standard fieldwork, grass samples, midday water potential.
|
Tonzi |
(152) 2018-06-01 10:30:00 |
Joe Verfaillie |
Installed FLIR A325sc thermal camera, check phenocams
|
Tonzi |
(143) 2018-05-23 11:00:00 |
Joe Verfaillie |
Standard data collection, lots of flowers, removed LED sensor and old LI-820 CO2 profile from the Tower.
|
Tonzi |
(143) 2018-05-23 10:00:00 |
Siyan Ma |
Standard field work, grass about 50% brown/yellow
|
Tonzi |
(131) 2018-05-11 11:00:00 |
Joe Verfaillie |
Installed Global Water logger at Road Well, problems with new CF card for phenocam image collection, standard fieldwork, midday water potential
|
Tonzi |
(115) 2018-04-25 10:30:00 |
Joe Verfaillie |
Missing Phenocam image, replaced clock batteries in zcam 2 and 3, checking solar equipment
|
Tonzi |
(115) 2018-04-25 09:00:00 |
Siyan Ma |
Very green, grasses maybe just passed peak, Ana did ASD spectra, standard fieldwork, midday water potential
|
Tonzi |
(103) 2018-04-13 10:00:00 |
Joe Verfaillie |
Standard field work, spectra library with ASD, first leaf water potential, removed northeast sap flow station.
|
Tonzi |
(103) 2018-04-13 09:00:00 |
Siyan Ma |
Standard field work, very green, first water potential measurements of the year, Ana did spectra at Tonzi
|
Tonzi |
(86) 2018-03-27 10:30:00 |
Joe Verfaillie |
Trees starting to put on leaves, fixed CR200, removed old well logger, turned off old Tower co2 profile, LAI-2200 measurements, replaced IRT tripod.
|
Tonzi |
(65) 2018-03-06 10:30:00 |
Joe Verfaillie |
Downgraded LI-7550 boxes, swapped 7500 heads, still trying to get of Tower co2 profile to run, still trying to get tower computer to run, still trying to get well and zcam 3 to run.
|
Tonzi |
(65) 2018-03-06 09:00:00 |
Siyan Ma |
Standard fieldwork, clip plots, swapped 7500 heads
|
Tonzi |
(59) 2018-02-28 11:00:00 |
Joe Verfaillie |
Installed Tower computer but no modem, upgraded power connections, updated GMP343 profile program, updated Floor well/zcam program
|
Tonzi |
(52) 2018-02-21 10:00:00 |
Joe Verfaillie |
Tried to set up Tower computer again, restarted old li-820 co2 profile, copied z-cam CR10X program.
|
Tonzi |
(52) 2018-02-21 09:00:00 |
Siyan Ma |
Standard fieldwork, lost Vaira Phenocam images,new well sensor
|
Tonzi |
(38) 2018-02-07 11:00:00 |
Joe Verfaillie |
Finished new Vaisala co2 profile, tried to install Latte Panda, Installed new well sensor, IRT tripod down - fixed.
|
Tonzi |
(38) 2018-02-07 09:00:00 |
Siyan Ma |
Unusually warm and sunny, missing images, new Tower co2 profile, new well sensor, clip plots, IRT tripod down - fixed.
|
Tonzi |
(15) 2018-01-15 11:30:00 |
Joe Verfaillie |
Partially installed new GMP343 co2 profile on the tower, removed the FD chamber for Tree 1 soil co2 profile.
|
Tonzi |
(15) 2018-01-15 10:00:00 |
Siyan Ma |
Foggy, standard fieldwork, removed Forced Diffusion chambers
|
Tonzi |
(3) 2018-01-03 10:45:00 |
Joe Verfaillie |
Fixed z-cam clocks, few Phenocam images
|
Tonzi |
(3) 2018-01-03 10:00:00 |
Siyan Ma |
Standard fieldwork, collected clip plots, calibrated soil co2 Vaisala
|