Site | Date | Author | Summary |
DWR Corn |
(349) 2012-12-14 14:00:00 |
Cove Sturtevant |
Downloaded data. Did spectral due to some grass patches. All good.
|
DWR Corn |
(341) 2012-12-06 10:00:00 |
Joe Verfaillie |
Quick site check.
|
DWR Corn |
(334) 2012-11-29 08:15:00 |
Cove Sturtevant |
Reinstalled ground sensors and put radiation boom out over the field. Downloaded data. Removed water pressure sensor for install at Twitchell. All well.
|
DWR Corn |
(320) 2012-11-15 11:00:00 |
Cove Sturtevant |
Corn has been harvested, chopped and baled. All checked out okay.
|
DWR Corn |
(315) 2012-11-10 12:45:00 |
Cove Sturtevant |
Enabled autocam, corn still waiting for harvest, readings looked okay.
|
DWR Corn |
(313) 2012-11-08 12:30:00 |
Cove Sturtevant |
Corn is being harvested. Data looks good. May not have camera pics for next week.
|
DWR Corn |
(304) 2012-10-30 11:45:00 |
Jaclyn Hatala |
Hundreds of ants and a few wasps in datalogger box
|
DWR Corn |
(299) 2012-10-25 14:35:00 |
Cove Sturtevant |
Pulled ground sensors for possible harvest. Downloaded data, took spectral measurements.
|
DWR Corn |
(292) 2012-10-18 14:00:00 |
Cove Sturtevant |
Tower readings good.
|
DWR Corn |
(285) 2012-10-11 13:45:00 |
Cove Sturtevant |
Corn is dry but some green hangs on, especially in certain patches. Downloaded data, took spectral and only green clippings.
|
DWR Corn |
(278) 2012-10-04 13:00:00 |
Cove Sturtevant |
All readings looked good. No plant measurements this week.
|
DWR Corn |
(271) 2012-09-27 13:30:00 |
Joe Verfaillie |
Collected data, spectral measurements, biomass
|
DWR Corn |
(264) 2012-09-20 13:00:00 |
Cove Sturtevant |
Corn is generally dry but still some green, 4-band radiometer PRT looks good after tightening connection in datalogger, Vaisala Temp/RH was about 0.5 C & 1.5% low, respectively, compared to standard.
|
DWR Corn |
(257) 2012-09-13 14:00:00 |
Cove Sturtevant |
Corn dry, tower readings good, Vaisala temp right on the standard, RH about 4 percentage points below the standard, wasps active around tower
|
DWR Corn |
(250) 2012-09-06 14:00:00 |
Joe Verfaillie |
Checked data, corn senescing, no fieldwork.
|
DWR Corn |
(243) 2012-08-30 11:45:00 |
Cove Sturtevant |
All looked good, corn drying out.
|
DWR Corn |
(236) 2012-08-23 15:00:00 |
Cove Sturtevant |
Corny! All A-OK. Corn was ready to eat.
|
DWR Corn |
(229) 2012-08-16 13:00:00 |
Joe Verfaillie |
Cobs still filling, standard field work, collected data.
|
DWR Corn |
(222) 2012-08-09 13:15:00 |
Joe Verfaillie |
Standard fieldwork, checked data.
|
DWR Corn |
(215) 2012-08-02 14:00:00 |
Joe Verfaillie |
Collected data, swapped 7500, moved tipping bucket, corn is flowering, standard fieldwork.
|
DWR Corn |
(208) 2012-07-26 01:00:00 |
Sara Knox |
Standard fieldwork
|
DWR Corn |
(201) 2012-07-19 13:30:00 |
Joe Verfaillie |
Collected data, standard field work, corn is about shoulder high.
|
DWR Corn |
(194) 2012-07-12 11:20:00 |
Sara Knox |
Standard fieldwork, checked data
|
DWR Corn |
(187) 2012-07-05 14:30:00 |
Joe Verfaillie |
Standard fieldwork, collected all data.
|
DWR Corn |
(181) 2012-06-29 14:30:00 |
Joe Verfaillie |
Ventilated HMP60, fixed autocam display setting, updated met program, moved moisture probes to staggerd depths.
|
DWR Corn |
(173) 2012-06-21 13:30:00 |
Sara Knox |
LAI, spectral, and clip plots measurements
|
DWR Corn |
(173) 2012-06-21 12:30:00 |
Joe Verfaillie |
Swapped radiometers, put radiometers on folding boom, moved eddy sensors to northwest corner, started autocamera.
|
DWR Corn |
(167) 2012-06-15 12:00:00 |
Joe Verfaillie |
Installed radiation boom, auto camera - no card, swapped 12VDC power stip, added security bolts to solar panels.
|
DWR Corn |
(165) 2012-06-13 13:15:00 |
Sara Knox |
Checked the site, took spectral measurements
|
DWR Corn |
(159) 2012-06-07 14:00:00 |
Joe Verfaillie |
Collected data, field work, moved upper boardwalk away from eddy sensors.
|
DWR Corn |
(152) 2012-05-31 10:00:00 |
Joe Verfaillie |
Moved ground sensors into the field, corn is up maybe some bald spots near the tower, fixed some wiring, did some field measurments.
|
DWR Corn |
(146) 2012-05-25 14:30:00 |
Joe Verfaillie |
Collected data, UC Davis in the field.
|
DWR Corn |
(142) 2012-05-21 10:30:00 |
Joe Verfaillie |
Installed solar system, met sensors at edge of field, installed flux sensors. Whendee checked site for chamber work.
|
DWR Corn |
(138) 2012-05-17 12:30:00 |
Joe Verfaillie |
In the beginning there was a scaffolding.
|