Equipment and Calibration

View History

Equipment Entry

Instrument:Interface
Manufacture:Campbell Sci.
Model No:NL115
Serial No:6761
Tag No:
Acquisition Date:2011-01-05
Project:DWR-Rice
Location on 2022-07-14:Lab,
Notes:

Documents

No documents found

History

Rec No.DateLoc FromTitleLoc ToNotes
5918 2022-07-14 Bouldin Corn Interface NL115 Removed Lab none Removed from BC and brought back to the lab for testing. The bottom 1/2-1/3 of phenocam photos is gray. Could be an interface or a card problem. It was replaced by sn 13056.
5904 2022-06-09 Lab none Installed Bouldin Corn Interface NL115 Installed on met CR1000 at BC and connected to Stardot phenocam
3117 2017-10-04 East End-Temp3 Interface NL115 Removed Lab none Removed with the decommissioning of Temporary Tower #3 - Boardwalk site.
2875 2017-06-23 Lab none Installed East End-Temp3 Interface NL115 Installed at the East End Temporary Tower #3 Boardwalk location with the initial setup of the site.
2785 2017-05-24 Tonzi-Floor Removed Lab none Removed from the Tonzi Floor tower. Replaced by the new Licor GHG system from Ameriflux.
1088 2013-10-18 Lab none Installed Tonzi-Floor Installed on the Tonzi Floor tower to replace sn 9774 that was having problems with its eject button.
1016 2013-05-15 Vaira Removed Lab none This NL115 was removed from Vaira along with CR1000 sn 47108 where they were used to collect images from the Starsot Phenocam. They were replaced by a Raspberry Pi
912 2013-01-24 Lab none Installed Vaira Installed the the computer box with CR1000 sn 47108 to collect images from the Phenecam
845 2012-11-08 West Pond Interface NL115 ATI Removed Lab none Removed from West Pond with the ATI sonic after a three week inter-comparison
846 2012-10-18 Sherman Island Interface NL115 ATI Installed West Pond Interface NL115 ATI Installed at West Pond with the ATI sonic for a three week inter-comparison
646 2012-02-15 Lab none Installed Sherman Island Installed on the CR1000 at Sherman to connect the LI7700. This replaced CFM100 sn 4994.