History for Siemens SP75 020854E-6-03-02-06862
Rec No. | Date | Loc From | Title | Loc To | Notes |
---|---|---|---|---|---|
6087 | 2022-11-02 | Bouldin Alfalfa-ADEX Solar Panel Edge A | Removed | Lab none | Removed from about 10m north of the Edge tower at the end of the 2022 advection experiment |
5873 | 2022-04-25 | Lab none | Installed | Bouldin Alfalfa-ADEX Solar Panel Edge A | Installed about 10m north of the Edge tower at -10cm for the advection experiment |
5739 | 2022-03-21 | Loaned none | Returned | Lab none | Returned from temporary setup on the Yampah Marsh at Elkhorn Slough. |
5577 | 2021-11-12 | Lab none | Loaned | Loaned none | Loaned to Adina Paytan at UCSC for temporary setup on the Yampah Marsh at Elkhorn Slough. |
5548 | 2021-10-26 | Vaira Solar Panel SoilCO2-B | Removed | Lab none | Removed from Vaira - not in use, was for old soil co2 system. |
5546 | 2012-02-16 | Lab none | Installed | Vaira Solar Panel SoilCO2-B | Installed to provide 24V power for soil CO2 system but mistakenly wired for 12V - fixed on 3/19 |
5544 | 2012-02-09 | Tonzi Solar Panel Floor H | Removed | Lab none | Removed from the Floor solar system. This panel has not been connected to the system since at least August 2008 |