Equipment and Calibration
View History
Equipment Entry
Instrument: | Soil Moisture Probe |
Manufacture: | Campbell Sci. |
Model No: | CS655 |
Serial No: | 17131 |
Tag No: | |
Acquisition Date: | 2015-09-28 |
Project: | CDFW |
Location on 2024-01-30: | Mayberry, |
Notes: |
12cm tines |
|
|
Documents
No documents found
Report: Soil VWC sensor lab calibration - 2022-02-25
History
Rec No. | Date | Loc From | Title | Loc To | Notes |
6559 |
2024-01-30 |
Lab none |
Installed |
Mayberry none |
Installed at MB in a tule patch southeast of the tower (~50cm from the staff gauge). This is a test to see if we can continuously track porewater salinity changes. |
6072 |
2022-11-02 |
Bouldin Alfalfa-ADEX Soil Moisture Probe Bouncer A |
Removed |
Lab none |
Removed from about 2m south of the Bouncer tower at -10cm at the end of the 2022 advection experiment |
5867 |
2022-04-25 |
Lab none |
Installed |
Bouldin Alfalfa-ADEX Soil Moisture Probe Bouncer A |
Installed about 2m south of the Bouncer tower at -10cm for the advection experiment |
5676 |
2022-02-03 |
Hill Slough Soil Moisture Probe B |
Removed |
Lab none |
Removed from Hill Slough because we weren't getting any interesting data from it--soils were staying saturated though the tidal cycle |
5191 |
2021-03-11 |
Lab none |
Installed |
Hill Slough none |
Installed at Hill Slough with site setup. Not sure of sensor depth yet (either -8cm or -16cm). |
4344 |
2020-01-30 |
East Pond Soil Moisture Probe B |
Removed |
Lab none |
Removed with the decommissioning of the EP tower and bought back to the lab. |
3428 |
2018-04-17 |
Lab none |
Installed |
East Pond Soil Moisture Probe B |
Installed at EP tower as part of initial site set up near profile B (South). |