4602 | 2020-07-09 | Loaned | Disposed | Disposed | Given to Sabina of Hydrofocus. The DWR grant ended at the end of June 2020, and Bryan requested we hand off a tower to Hydrofocus. |
4572 | 2020-07-09 | Sherman Barn PAR Sensor Reflected | Removed | Loaned none | Removed from Sherman Barn with its decommissioning and given to Sabina of Hydrofocus. The DWR grant ended at the end of June 2020, and Bryan requested we hand off a tower to Hydrofocus. |
3580 | 2018-07-11 | Lab none | Installed | Sherman Barn PAR Sensor Reflected | Installed at Sherman Barn on the radiation boom just outside the southwest corner of the cow fence. This is the initial set up of the site. |
3519 | 2018-06-13 | Twitchell Alfalfa PAR Sensor Incoming | Removed | Lab none | Removed with Twitchell Alfalfa site decommissioning. |
1001 | 2013-05-24 | Lab none | Installed | Twitchell Alfalfa PAR Sensor Incoming | Installed at the Twitchell Alfalfa site. This PAR sensor is mounted to measure incoming PAR. This sensor is on the radiation post in the field west of the scaffolding. |
651 | 2012-06-21 | DWR Corn | Removed | Lab none | Removed from the upward facing position on the Cron tower. It was replace with sn 110340 that had a longer cable spliced on to it. |
612 | 2012-05-21 | Lab none | Installed | DWR Corn | Installed on a temporary boom at the top northwest corner of the scaffolding at the DWR Corn site. The sensor is facing upward collecting incoming PAR. |