Equipment and Calibration History

History for Siemens SP75 020854E-6-03-02-06905

Rec No.DateLoc FromTitleLoc ToNotes
5820 2022-05-04 Lab none Repair Lab none This panel had been under (salt) water at Yampah. The junction box on the back was all rotted out. I scraped the box off and the four junctions to the two 6V cell strings were still good. I soldered wires to the junction pads and added a screw terminal with two diodes. The panel was 20V and 4.5A in the sun. I cut the structure out of the junction box and reglued it to the back on the panel to protect the wiring and screw terminal. I think this panel is good to go.
5740 2022-03-21 Loaned none Returned Lab none Returned from temporary setup on the Yampah Marsh at Elkhorn Slough.
5578 2021-11-12 Lab none Loaned Loaned none Loaned to Adina Paytan at UCSC for temporary setup on the Yampah Marsh at Elkhorn Slough.
5547 2021-10-26 Vaira Solar Panel SoilCO2-A Removed Lab none Removed from Vaira - not in use, was for old soil co2 system.
5545 2012-02-16 Lab none Installed Vaira Solar Panel SoilCO2-A Installed to provide 24V power for soil CO2 system but mistakenly wired for 12V - fixed on 3/19
5543 2012-02-09 Tonzi Solar Panel Floor G Removed Lab none Removed from the Floor solar system. This panel has not been connected to the system since at least August 2008