History for Handar 425A 0860
Rec No. | Date | Loc From | Title | Loc To | Notes |
---|---|---|---|---|---|
7028 | 2024-11-13 | Lab none | For Resuse | Lab none | Marked for reuse |
1804 | 2015-04-29 | Tonzi | Removed | Lab none | Removed from the 3.89m location on the wind profile due to bad data. This is the sonic the was banged previously. |
1770 | 2015-04-08 | Lab none | Installed | Tonzi | Installed at 3.89m agl in a wind profile near the Floor tower. |
490 | 2011-12-23 | Lab none | Tested | Lab none | Tested with other Handar sonics by placing each sonic at 17cm, 48cm, 78cm and 108cm from a blower. All sonics gave similar resonable readings. |
479 | 2011-04-10 | Loaned | Returned | Lab none | Returned by Sara Winsemius. Sara reports that it was banged twice and no longer reports resonable wind speed. |
478 | 2011-04-08 | Lab none | Loaned | Loaned | Loaned with a CR10X to Sara Winsemius for a class project. |
476 | 2008-12-11 | Tonzi-Tower | Removed | Lab none | Removed with the Tonzi Tower wind profile. |
471 | 2003-08-01 | Lab none | Installed | Tonzi-Tower | Installed on the Tonzi Tower as part of a wind profiles with sonics at 10.61m, 11.76m, 13.21m, 15.04m and 16.86m. |