Bouldin Corn: 2017-04-26 10:30:00 (DOY 116)
Author: Joe Verfaillie
Others: Daphne, Sam, Kyle

Summary: Initial set up of this site, installation on power line, waiting on end of tractor work before moving soil sensors into the field.

Bouldin Corn
2017-04-26

I arrived about 10:30 with Daphne, Sam and Kyle. Today is the initial setup of this site. It was cloudy and drizzly at first but after lunch it became party cloudy and very windy with gusts to 11m/s. The fields to the west are completely plowed. The field to the east has a small patch near the duck club building still unplowed possibly because it was too wet. It does not look like the fields have been planted yet.

Kyle and Sam took the truck to get the scaffolding we left by the south pump station while Daphne and I started on the power line. We ran a two conductor #10 with ground UF-B direct burial cable from the breaker panel at the east end of the building to the southeast corner of field 48. We stapled the cable to the building and porch near the ground. We used a rented trencher to dig a 12in deep trench from the northwest corner of the porch, just past the end of a north-south drainage ditch to the tower location. It crosses both roads at a diagonal. The cable is in 3/4in plastic conduit at the bottom of the trench. At the building I added a 20A breaker to the electrical panel to supply our line. A Campbell enclosure on the tower holds a box with four standard outlets and a lab power supply for 12VDC.

The tower went up as planned. Two levels of 5ft frames with railings on top. We did not have the cross braces for the railings so we tried to manufacture some from 3/4in metal conduit, but the drill battery kept dying. One length still needs to be installed. The soil sensors are all installed near the southern edge of the scaffolding to protect them from any more tractor work. They will be move out into the field later.

Equipment
Licor 7500A sn 75H-2182 (5.2m height, 36cm ESE of sonic)
Licor 7550 sn AIU-1570 (needs pressure coefficients label, updated from database entry)
Licor 7700 sn TG1-0421 (5.2m height, 37cm E of sonic)
Gill WM sn 074417 (sonic heading is 0deg true north)
NR01 sn 2420
PAR in sn 140453
PAR out sn 140441
SHFP-1 sn 10867
SHFP-2 sn 11326
SHFP-3 sn 10861
HMP60 sn L1740395 (on LI-7500 post)
PTB 110 Barometer sn L2340502
Tipping Bucket sn 65548-615 (top southeast corner of scaffolding)
ML3 theta probe sn M003370
CS655 TDR_A sn 17129
CS655 TDR_B sn 17128
CS655 TDR_C sn 17133
SRS PRI in A sn 913003004
SRS PRI out B sn 897103002
SRS NDVI in C sn 882103020
SRS NDVI out D sn 943103015
SoilT Profile A -2, -4, -8, -16, -32cm
SoilT Profile B -2, -4, -8, -16, -32cm
SoilT Profile C -2, -4, -8, -16, -32cm
CR1000 sn 66251
CFM NL115 sn 13056
AM16/32 sn 21690
AM25T sn 7908

The 7500 read: 403.7ppm CO2, 661.1mmol/m3 H2O, 21.2C, 101.6kPa, 86.2SS
The 7700 read: 1.92ppm CH4, 63.5RSSI – 75.1 after cleaning

The CR1000 data looked normal, Campbell VWC: 0.25-0.31, Theta probe 700mV

4 photos found

view of field site
20170426BC_Trench.jpg ( 2017-04-26 12:48:29 ) Full size: 1440x1920
view of field site

view of field site
20170426BC_TowerDone.jpg ( 2017-04-26 16:10:18 ) Full size: 1440x1920
view of field site

view of field site
20170426BC_SonicHeading.jpg ( 2017-04-26 16:13:16 ) Full size: 1440x1920
view of field site

view of field site
20170426BC_SettingUp.jpg ( 2017-04-26 12:27:59 ) Full size: 1920x1440
view of field site

Graphs display:
6 sets found

No data found for BC_met.
No data found for BC_flux.
Can't check TATWBABCSB_cam
Can't check MBSWEEWPBCBA
No data found for BC_pa.
No data found for BC_arable.

 
 

Login
Select Notes:

This material is based upon work supported by the National Science Foundation and US Department of Energy. Any opinions, findings, conclusions, or recommendations expressed in the material are those of the author(s) and do not necessarily reflect the views of the supporters.