Field Notes
<--2015-04-23 09:00:00 | 2015-05-12 09:00:00-->Other sites visited today: Mayberry | Twitchell Rice | East End | West Pond | Twitchell Alfalfa
Phenocam link: Searching...
Sherman Island: 2015-05-07 09:00:00 (DOY 127)
Author: Cove Sturtevant
Others: Sara
Summary: New wetland construction. Shut down tower and pulled power. Need to pull tower next week.
Sherman 2015-05-07 We arrived around 9:00 PDT. New wetland construction has begun. They were grading around the tower and pulled up the power lines, but power was still running when we arrived. We grabbed CR1000 data logger sn 4017 and CFM100 sn 4993 and computer. Removed the power lines and electric fence around the power pole and shut down the site. Met Jesse (916) 715-8699 who said we should be fine to pull the tower next week, though he asked that we call him the day before and be sure to grab hard hats and vests from the trailer when we arrive. |
3 photos found
20150507SI_Tractors.jpg ( 2015-05-07 09:49:12 ) Full size: 1920x1080
Tractors on site beginning wetland construction
20150507SI_Cove.jpg ( 2015-05-07 09:48:50 ) Full size: 810x1440
Cove on site messing with the power
20150507SI_Sara.jpg ( 2015-05-07 13:35:21 ) Full size: 864x1152
Sara on site
7 sets found
No data found for SI_mp.
11 SI_met graphs found
Can't check SI_mixed
2 SI_mixed graphs found
4 SI_flx graphs found
No data found for SI_soilco2.
Can't check TWSI_mixed
Can't check SIMBTWEE_met