Equipment and Calibration History

History for MorningStar PS-30M 02431248

Rec No.DateLoc FromTitleLoc ToNotes
3397 2017-06-02 Lab none Tested Lab none I tested this controller in the lab and talked with a Morningstar technician. The consensus is that something failed on the board that disabled the load. It might be fine for charging batteries though.
2220 2016-03-08 Tonzi-Tower Removed Lab none This charge controller was at the Tonzi Tower. It could not read the battery bank voltage and had shutdown the load with a Low Voltage Disconnect message. I removed it and replaced it with the controller from the Tram system sn 0135002X