5832 | 2022-05-10 | Vaira Battery Bank Main | Maintenance | Vaira Battery Bank Main | Fixed broken wire between the two banks of solar panels. Disconnected and load tested all the batteries. Two batteries, second from north in each box, tested bad. These were moved to the north most position and left disconnected. The other six tested good and were reconnected. |
2333 | 2005-12-13 | Vaira | Upgrade | Vaira | Six old gel cell batteries were removed and will be added to Tonzi Tower. Eight new gel cell batteries installed. The new batteries are Maxrate Premium Plus MT12-350. Valve regulated lead acid battery 12v 93 ah @ 20 hr rate. Bought from Nor-Cal Battery for 5 ea.
|
4929 | 2003-12-19 | Vaira Battery Bank Main | Upgrade | Vaira Battery Bank Main | Cleaned battery terminals and added four batteries from the Floor site for a total of 12 at Vaira. |
4896 | 2003-02-13 | Vaira Battery Bank Main | Upgrade | Vaira Battery Bank Main | Added four batteries removed from Tonzi-Tower. Now a total of eight batteries. |