5701 2022-02-18 Lab none Installed Gilbert Tract Solar Panel ADCP Installed near the Gilbert Tract breach to measure tidal current
5691 2022-02-09 Tonzi Removed Lab none Removed from OSU SP2 with the dying battery. Replaced with a power line from the Tower battery bank.
3652 2012-01-09 Lab none Installed Tonzi Installed at SP2 near the Tower. This is the initial setup of the site by Richard Cuenca and Yutaka Hagimoto of Oregon State Univ.