| ALL | | Anemometer || Barometer || Battery Bank || Camera || CO2 Probe || Conductivity Sensor || Data Logger || DO Sensor || Gas Analyzer || Heat Flux Plate || Interface || Multiplexer || Narrow Band || Net Radiometer || PAR Sensor || RH & Temp || Soil Moisture Probe || Solar Controller || Solar Panel || Water Level |

SELECT a.recno, a.eh_date, a.eh_loc1, a.eh_loc2, IF(a.eh_loc2=:loc, a.eh_locref2, a.eh_locref1) AS ref, a.eh_locref2, a.eh_title, a.eh_notes, a.eh_id, b.serialno, b.equip, b.modelno FROM equiphist a INNER JOIN equiplist b ON a.eh_id=b.recno WHERE (a.eh_loc1=:loc1 OR a.eh_loc2=:loc2) AND b.equip=:eq ORDER BY b.serialno, a.eh_date

Date Serial No. Model Action Ref Notes
Solar Panel
2018-04-17 11ZV0M0829 KD140SX-UFBS Installed Solar Panel A Installed at EP tower as part of initial site set up about 12m NNW of the tower
2020-01-30 11ZV0M0829 KD140SX-UFBS Moved Solar Panel A Removed with the decommissioning of the EP tower and installed at the new SW Temporary site 1250m upwind of the Permanent Tower.
2018-04-17 11ZV0M0836 KD140SX-UFBS Installed Solar Panel B Installed at EP tower as part of initial site set up about 12m NNW of the tower
2020-01-30 11ZV0M0836 KD140SX-UFBS Moved Solar Panel B Removed with the decommissioning of the EP tower and installed at the new SW Temporary site 1250m upwind of the Permanent Tower.
2018-04-17 11ZV0M0855 KD140SX-UFBS Installed Solar Panel C Installed at EP tower as part of initial site set up about 12m NNW of the tower
2020-01-30 11ZV0M0855 KD140SX-UFBS Moved Solar Panel C Removed with the decommissioning of the EP tower and installed at the new SW Temporary site 1250m upwind of the Permanent Tower.