| ALL | | Anemometer || Barometer || Battery Bank || Camera || CO2 Probe || Conductivity Sensor || Data Logger || DO Sensor || Gas Analyzer || Heat Flux Plate || Interface || Multiplexer || Narrow Band || Net Radiometer || PAR Sensor || RH & Temp || Soil Moisture Probe || Solar Controller || Solar Panel || Water Level |

SELECT a.recno, a.eh_date, a.eh_loc1, a.eh_loc2, IF(a.eh_loc2=:loc, a.eh_locref2, a.eh_locref1) AS ref, a.eh_locref2, a.eh_title, a.eh_notes, a.eh_id, b.serialno, b.equip, b.modelno FROM equiphist a INNER JOIN equiplist b ON a.eh_id=b.recno WHERE (a.eh_loc1=:loc1 OR a.eh_loc2=:loc2) AND b.equip=:eq ORDER BY b.serialno, a.eh_date

Date Serial No. Model Action Ref Notes
Battery Bank
2018-04-17 BB-EP BB-Fab Installed Battery Bank This is the initial installation of this battery bank. The batteries are from Mayberry and are rather old with dates of July 2010 on them. They were removed from Mayberry when the power failed there but that was probably due to a broken wire rather than weak batteries. The batteries sat idle in the lab for a month or so and didn't seem to lose much charge. Some of them were charged up just before deployment.
2018-07-05 BB-EP BB-Fab Maintenance Battery Bank This battery bank has been loosing power over night. We disconnected all the batteries and tested each one with the load tester. Two tested weak, were removed and brought home. These two may have been the ones lowest on water last time.
2018-07-17 BB-EP BB-Fab Upgrade Battery Bank I turned off all the solar power and removed the four remaining size 27 batteries. These batteries were from Mayberry and were about seven years old. I replaced them with five brand new (July 2018 tags) size 31 Duracell deep cycle batteries. These are part number SLI31MDC and have a capacity of 105Ah. Size 27 are rated at 90Ah, so about the same capacity as six size 27s. After the swap the solar panels were feeding the batteries 20A.
2020-01-30 BB-EP BB-Fab Disposed Battery Bank Removed with the decommissioning of the EP tower, so BB-EP will cease to exist. This equipment will be used at the new SW Temp1 tower and be rechristened BB-SW_Temp1
2020-01-20 BB-SW_Temp1 BB-Fab Installed Battery Bank Installed with the initial setup up of the tower. Parts last used at the East Pond site. Five size 31 Duracell deep cycle batteries (July 2018 tags). These are part number SLI31MDC and have a capacity of 105Ah. 12VDC system.