History for Handar 425A 0852

Rec No.DateLoc FromTitleLoc ToNotes
7027 2024-11-13 Lab none For Resuse Lab none Marked for reuse
2132 2015-12-23 Tonzi Removed Lab none Removed from the bottom location of the wind profile near the Floor tower.
1772 2015-04-08 Lab none Installed Tonzi Installed at ~1.2m agl in a wind profile near the Floor tower.
491 2011-12-23 Lab none Tested Lab none Tested with other Handar sonics by placing each sonic at 17cm, 48cm, 78cm and 108cm from a blower. All sonics gave similar resonable readings.
481 2011-05-02 Loaned Returned Lab none Returned by Sara Winsemius.
480 2011-04-10 Lab none Loaned Loaned Loaned to Sara Winsemius for a class project.
477 2008-12-11 Tonzi-Tower Removed Lab none Removed with the Tonzi Tower wind profile.
472 2003-08-01 Lab none Installed Tonzi-Tower Installed on the Tonzi Tower as part of a wind profiles with sonics at 10.61m, 11.76m, 13.21m, 15.04m and 16.86m.